Client:Private
Sector:Residential
Project:Thurloe Lodge, Knightsbridge
Scope:

Dismantling, piling, underpinning etc. The project includes the dismantling of existing property, underpinning and temporary support to existing structures, piling works and a top down basement construction followed by a new RC frame for the new property. The new basement levels created will include an underground swimming pool.

Value:£2.7M
Duration:13 months

Project Update

16 Aug, 2016

We have now excavated down to the first basement level. We are forming a concrete slab and will then dig underneath that slab in what is called a "top down" method to the lower levels. The green shading of the 3D model shows the floors below ground level and the photo shows us working at first basement level. Lots more to do but progressing well.