Euro-City is assisting Graham Construction in this project with the set up of the site, all drainage infrastructure from roadways to new buildings and services.

Our role in this project has been to assist with the set up of the site.  To install new drainage infrastructure from roadways to new school buildings. Install underslab and in-slab drains and services.  We have formed new reinforced concrete raft foundations and slab for new school buildings.

As of 30th September 2019 we have commended the final concrete raft pour which forms the spine of the new Western Expansion Secondary School.  This is over 3000 cubic metres of concrete and 350 tonnes of new reinforcement and all completed two weeks ahead of schedule for our client, Graham Construction.  

At the same time we are installing sitewide drainage and services infrastructure, form kerbing, paving and external works as well as a new car park.